I'm looking for suggestions about how to upgrade a vented cathedral ceiling covered with very nicely finished (albeit leaky) tongue and groove pine. Some specifics:


About 1/2 the assembly is vented from eave to ridge. The other 1/2 is tied into an accessible attic flat. Presumably, the 14" TJI's have poorly installed styrofoam proper vents. I don't believe they go all the way to the ridge and are not air sealed at all.


The 14" TJI is insulated with faced FGB (12"). The facing is installed to the warm side of the home.


There is a metal roof and the customer has no intention (or budget) to remove it and install rigid on the roof.


The tongue and groove is finished nicely with several coats of clear coat. It's a high end home and this assembly needs to be put back together perfectly.


The ceiling is peppered with recessed lights.


Each slope is 14' long and the room is 26' long.


I've noodled around with a few options based on the customer's budget and what we're hoping to achieve. They run the gamut from removing the T&G and FGB, installing sheetrock as an air barrier, dense packing the cavity, and re-installing the T&G. The ridge and eaves would be blocked and we'd have a hot roof. Moisture load in the home in low and managed.


Another option was to access the eave and ridge and 2 other area but removing strips of T&G. We'd then remove the FGB, block eaves and ridge, install 1" of CCF on the back side of the T&G (as an air barrier) and dense pack the cavity with cell. Might trap moisture, though?


How about removing sections of the T&G, removing FGB, and adding 3" of CCF to the underside of the roof then dense packing and re-installing T&G? Not a perfect air barrier but the likelihood of condensation is reduced from the foam.


Straight up dense pack the assembly? Just block the soffits/ ridge and keep the FGB?


I think creating a hot roof makes sense as it would be challenging to install a continuous vent from eave to ridge.


Like all T&G, the corners are leakiest although in this assembly, it was all leaky during my BD test.
Tongue and groove cathedrals without a proper air barrier (and poorly/ incorrectly vented) are a bugger! If anyone has any ideas on a reasonable way to make this assembly perform better, I'm open to suggestions.
Thanks!
Matt

Views: 183

Replies to This Discussion

I hate to say this but budget wise & for looks, it would be easier, cleaner & cheaper to attack it from above. If you do remove the T&G look into a tool called the extractor as it is great at pulling the nails from the back

I don't know what the codes or exactly which climate zone where you are at in Maine but you need at least R20 air impermeable insulation added to either the underside or on top of the roof sheathing. If you come at it from below I would spray foam whereas from above I would lean more towards foam sheathing - 2 layers with offset seams For more: http://bit.ly/HotRoof 

Hi Matt,

Always super tough to fix these after they have been done so very wrong.  Tom Nichols just had a long thread on Linkedin on this very subject.  I didn't keep up with all of the posts but it might offer some advice.  I will read it later and re-post.

http://www.linkedin.com/groupItem?view=&srchtype=discussedNews&...

Can lights, no air barrier, and fiberglass insulation open to the flow of ventilation, not good.  R&R that T&G is going to be a bear, especially after it has been "finished nicely with several coats of clear coat".  Also, if that TJI is spaced 16" or 24" oc, then normal batt insulation does a poor job of filling the space between.  They make wider batts, but even with those it doesn't conform well around the bottom chord. 

I would avoid just dense packing what is there, moisture will still pass through the cellulose.  Any form of a hot roof, as Sean said, needs a substantial layer of spray or rigid foam to keep the inside surface above the dew point.  I'm assuming this is a year round home, not seasonal.

Back later.

Bud

The topic has been discussed ad infinitum at the linkedin group Bud shared.  I see this a lot; "High end home, but low budget."  Ironic to me.  If they want it fixed they need to pay the freight.  Do it right, or don't do it at all (or you'll buy it.)  My take; remove the t&g, throw the can lights away, remove the venting, install code-required insulation at a minimum, install drywall with finished joints/edges (durable air barrier), make provision for surface-mount light fixtures, reinstall the t&g, or find another nifty looking high-end finish product, and they'll likely go for it in a minute.

Hi Matt,

If you checked out Bud's link I'm sure you saw all of the ideas folks have on this.  Definitely no clear cut answers.  I would vote for the least intrusive method of opening the soffit, removing as much FGB you can and dense packing the rest to slow/stop air movement.  Reassemble and seal vent. 

For the lights, replace with sealed LED retrofits and caulk them in.

It's a tough situation no doubt.  Good luck

RSS

Home Energy Pros

Home Energy Pros was founded by the developers of Home Energy Saver Pro (sponsored by the U.S. Department of Energy,) and brought to you in partnership with Home Energy magazine.

Latest Activity

Jim Gunshinan posted blog posts
9 hours ago
H.O. Electric posted a photo

about us-team

H.O. Services is your residential Electric-Plumbing-Heating-Cooling Specialist. We are an…
9 hours ago
H.O. Electric added a discussion to the group News & Announcements
Thumbnail

Stay Cool With Easy To Install Ductless AC System!

Stay Cool With Easy To Install Ductless AC System!   Save $300.00 Off A New AC System For A Limited…See More
9 hours ago
Richard Wells commented on Diane Chojnowski's group Facebook Pages
"Three thousand home energy efficiency audits, and nearly a thousand retrofits in four short…"
11 hours ago
Richard Wells joined Diane Chojnowski's group
Thumbnail

Facebook Pages

Does your company or organization have a Facebook Page?This group is for pros who have facebook…See More
11 hours ago
David Baerg replied to Blake Shurtz's discussion Air sealing wood-burning fireplace from the crawlspace below
"Hi Blake, Do you mean around the underside of the hearth?  Are you trying to seal between the…"
12 hours ago
Tom White's video was featured

Rebirth Realty: Restoring Detroit properties for Venture for America Fellows

Its been a long, cold winter, but we've made significant progress in the restoration of 760 Virginia Park. Join Tim Dingman on a walkthrough to see what we've done.
13 hours ago
Kim Tanner added a discussion to the group Multifamily Buildings
Thumbnail

Blower Door Applications Guide

TEC and Camroden Associates have released their big building testing manual, Blower Door…See More
13 hours ago
Profile Iconmichael coleman, Dan Liska and Rob Moreno joined Home Energy Pros
14 hours ago
Christopher Morin's blog post was featured

5 Things New Energy Efficiency HVAC Contractors Need to Know

1. Do not sell on Price! Use 'Simple Payback'The price of High-efficient equipment will undoubtedly…See More
yesterday
Jim Gunshinan's blog post was featured
yesterday
Kim Tanner commented on Diane Chojnowski's group Home Energy Pros on Twitter
"Follow The Energy Conservatory on Twitter! We'll follow…"
yesterday

© 2014   Created by Lawrence Berkeley National Laboratory.

Badges  |  Report an Issue  |  Terms of Service