Hello pros.

Please see the attached pictures.

Any insights on how you would insulate the 2nd story walls of this house? The house is located in the suburbs of Washington D.C.

Thanks!

Patrick

Views: 1213

Reply to This

Replies to This Discussion

Mr. Poll,

I'd take your list for our climate and edit it down to:

4.  As always with ice dams, air sealing and insulation are the first concerns.  Once that is done, then venting can be addressed.

6. Air tightness test and IR can your insulation and air barrier work. If good, drywall.

5. Ignore venting especially in lower slopes.

Have done a few of these in my time. Not easy, but can be done. I have taken 2 rows of shingles off, difficult because you have to get nails from not only the course you want to remove, but also, the row above that. Once the row is removed, I cut a 3 inch square out of the top of the course that is showing and keep that to be replaced. Drill your holes, fill with cellulose, install a tapered wooden plug, cover the plug with roof tar, replace the square you cut out earlier, cover this with a thin coat of roof tar, reinstall your shingle. Labor intensive, but I have had great success with it. Good luck.

Robert

It seems that you describe filing the entire cavity between the vertical interior wall and the steeply pitched lower roof with insulating material - is this correct?  How much insulation is this?  How do you ensure that you have sealed the open joist cavity ends?  In some of these built in recent times, we have seen the plywood interior subfloor extend out to the steeply angled roof so that filling the cavity with insulation does not address the open cavities - and these are the biggest problem with this type of mansard.  Second biggest problem in this particular case is the open party wall at both ends of the house (In this case, just one end because it is an end-row unit).  This open party wall would need some dense-packing.  Both the party wall and the joist cavities are the source of all the moisture that might be in the lower attic - in this DC climate.

You could then drill a 1 inch hole thru the soffit and fill the open end of the floor joists. If the soffit is large enough, drill your normal sized hole and fill it, plug, and patch. You can expect to go thru alot of material as the lower portion flairs out. Anything can be done, only limitations are your comfort levels.

Yikes. It is never as straightforward as one would hope in these "do it right" retrofits. The homeowner is getting itchy about implementing the work, especially because he has been given much misinformation (so it appears) from other "blow it and roll" contractors.

I may have to walk away from this one if he feels confident enough to just settle with more insulation is better than no insulation.

Patrick

Ed,

You put your finger on it: air seal floor cavity! The volume is triangular and the weight and force with dense pack will be borne by the soffit. I love cellulose, but may be best to open it up from below (or if re-roofing pull back the sheathing), do some air sealing and ensure your duct runs are"inside" the house.

Robert,

Very good idea. I have experience with patching roofs and re-roofing so that part will not be a problem.

Much preferred to the going through drywall route, and later having to patch and paint.

Happy holidays!

Patrick

Ok, What has happened since? 

RSS

Home Energy Pros

Home Energy Pros was founded by the developers of Home Energy Saver Pro (sponsored by the U.S. Department of Energy,) and brought to you in partnership with Home Energy magazine.

Latest Activity

Jim Gunshinan commented on Jim Gunshinan's blog post Energy Upgrade California—Up Close and Personal
"I had a revelation while attending Bruce Manclark's session of duct leak testing at the Energy…"
7 hours ago
George J. Nesbitt commented on Jim Gunshinan's blog post Energy Upgrade California—Up Close and Personal
"Blower Door; the 2007 test was a depressurization test, and the 2014 a pressurization test, which…"
7 hours ago
George J. Nesbitt replied to Kaushal Bharath Raju's discussion Affordability & Deep Energy Upgrade/Passive House Retrofit in Berkeley, California.
"Plan, plan, plan, plan. The 1st step to is to understand the house, how it's built, the…"
7 hours ago
George J. Nesbitt posted an event

High Performance Windows - A Panel of Experts at Pyramid Alehouse`

April 26, 2014 from 3pm to 5pm
Join a lively panel discussion on high performance windows. We'll cover some basics, as well as…See More
9 hours ago
Kaushal Bharath Raju replied to Kaushal Bharath Raju's discussion Affordability & Deep Energy Upgrade/Passive House Retrofit in Berkeley, California.
"Hi David, Thanks for pointing out Martin Holiday's article. I do not wish to engage in the…"
9 hours ago
Profile IconAdam Penberthy, Scot Davidson and j jarvella joined Home Energy Pros
9 hours ago
David Eakin replied to Kaushal Bharath Raju's discussion Affordability & Deep Energy Upgrade/Passive House Retrofit in Berkeley, California.
"More food for thought on this subject - read this (fairly) recent blog by one of the most respected…"
14 hours ago
Curt Kinder commented on Christopher Morin's blog post 5 Things New Energy Efficiency HVAC Contractors Need to Know
"You left out air distribution...Without at least a passing glance at how much air moves through the…"
20 hours ago
David Eakin replied to Kaushal Bharath Raju's discussion Affordability & Deep Energy Upgrade/Passive House Retrofit in Berkeley, California.
"I mis-spoke - I was referring to the Midori House in Santa Cruz. Have an in-depth discussion with…"
yesterday
Kaushal Bharath Raju replied to Kaushal Bharath Raju's discussion Affordability & Deep Energy Upgrade/Passive House Retrofit in Berkeley, California.
"Hi David & Bud, $400/sqf > $300 sqf. The latter is the minimum cost of new construction in…"
yesterday
David Eakin replied to Kaushal Bharath Raju's discussion Affordability & Deep Energy Upgrade/Passive House Retrofit in Berkeley, California.
"Kaushal, There was a deep energy retrofit upgrade project (to Passive House standards) in San Jose…"
yesterday
Kim Tanner updated an event

Beyond Residential Testing at The Energy Conservatory

May 14, 2014 to May 16, 2014
The Energy Conservatory (TEC) is hosting a Beyond Residential Testing event. In addition we are…See More
yesterday

© 2014   Created by Lawrence Berkeley National Laboratory.

Badges  |  Report an Issue  |  Terms of Service