Hi There Folks,


I came across this crawlspace vapor barrier installed by a BPI contractor. 

Location:  Bay Area of California- near the ocean.  

Environmental Factors:  The area receives a lot of rain, and is notorious for rising groundwater.  

Health Factors:  The customers have respiratory issues, and these were communicated to the contractor.

Material:  6mm visqueen, red tape, nails

Concerns:  The material stops several inches short of the foundation walls. Some seams are taped with red tape.  Held to ground with 8 inch nails. 

I have a lot of respect for this particular contractor, but I have grave questions about how he approaches barrier installation in crawl spaces.

He has responded that this approach is adequate for unconditioned crawlspaces.  


I would appreciate insights, and direction to standards. 

Tags: barrier, crawl, space, vapor

Views: 11739

Attachments:

Replies to This Discussion

I am not sure what the codes say in Cali but (unless I am overlooking it) there is no requirement in the 2009 IRC or IECC for "vented" crawls

For sealed crawls it is;

R408.3.1 Exposed earth is covered with a continuous Class I vapor retarder. Joints of the vapor retarder shall overlap by 6 inches (152 mm) and shall be sealed or taped. The edges of the vapor retarder shall extend at least 6 inches (152 mm) up the stem wall and shall be attached and sealed to the stem wall;

As for the groundwater issue:

R408.6 Finished grade. The finished grade of under-floor surface may be located at the bottom of the footings; however, where there is evidence that the groundwater table can rise to within 6 inches (152 mm) of the finished floor at the building perimeter or where there is evidence that the surface water does not readily drain from the building site, the grade in the under-floor space shall be as high as the outside finished grade, unless an approved drainage system is provided.

As for best practices, especially when a respiratory issue is involved - it is basically what everyone else mentioned - run up the foundation wall a minimum of 6", joints lapped lapped, and every hole, seam, etc... should be taped & sealed per manufacturers directions

RSS

Videos

  • Add Videos
  • View All

Twitter

Latest Activity

Simon joined Diane Chojnowski's group
Thumbnail

Online Training

Online training coursesIf you provide ongoing online training for home performance or…See More
5 hours ago
Simon added a discussion to the group Energy Auditing Equipment for Sale, Trade or to Purchase
Thumbnail

Wanted - Blower and door frame kit for Minneapolis system

Hi everyone,I'm new to this line of work and have bought some equipment (Minneapolis blower door…See More
12 hours ago
Simon replied to Steve Mann's discussion TEC Blower Door Frame in the group Energy Auditing Equipment for Sale, Trade or to Purchase
"Hi, I'm interested, but could you send to UK?,I'd pay shipping of course. My email is :-…"
13 hours ago
Simon replied to Jeffrey Anthony's discussion Blower Door Equipment - 9 shrouds, 10 fans, 5 fan controllers in the group Energy Auditing Equipment for Sale, Trade or to Purchase
"Hi, if you able to sell sepereately, I'd be interested in a blower and a frame kit. My only…"
13 hours ago
Simon joined allen p tanner's group
Thumbnail

Energy Auditing Equipment for Sale, Trade or to Purchase

Discuss the pros and cons of the equipment you are interested in prior to purchase. Post equipment…See More
13 hours ago
Simon is now a member of Home Energy Pros
17 hours ago
Rob Madden, Solar Home Broker joined Leslie McDowell, BPI's group
Thumbnail

Building Performance Institute (BPI)

BPI is the nation's premier standards development, quality assurance and credentialing organization…See More
yesterday
Rob Madden, Solar Home Broker posted a discussion

Indoor Air Quality Monitors and Meters

I'm considering purchasing the AirAdvice for Homes indoor air quality monitor but it seems to have…See More
yesterday

© 2016   Created by Lawrence Berkeley National Laboratory.   Powered by

Badges  |  Report an Issue  |  Terms of Service