Hi There Folks,


I came across this crawlspace vapor barrier installed by a BPI contractor. 

Location:  Bay Area of California- near the ocean.  

Environmental Factors:  The area receives a lot of rain, and is notorious for rising groundwater.  

Health Factors:  The customers have respiratory issues, and these were communicated to the contractor.

Material:  6mm visqueen, red tape, nails

Concerns:  The material stops several inches short of the foundation walls. Some seams are taped with red tape.  Held to ground with 8 inch nails. 

I have a lot of respect for this particular contractor, but I have grave questions about how he approaches barrier installation in crawl spaces.

He has responded that this approach is adequate for unconditioned crawlspaces.  


I would appreciate insights, and direction to standards. 

Tags: barrier, crawl, space, vapor

Views: 12283

Attachments:

Replies to This Discussion

I am not sure what the codes say in Cali but (unless I am overlooking it) there is no requirement in the 2009 IRC or IECC for "vented" crawls

For sealed crawls it is;

R408.3.1 Exposed earth is covered with a continuous Class I vapor retarder. Joints of the vapor retarder shall overlap by 6 inches (152 mm) and shall be sealed or taped. The edges of the vapor retarder shall extend at least 6 inches (152 mm) up the stem wall and shall be attached and sealed to the stem wall;

As for the groundwater issue:

R408.6 Finished grade. The finished grade of under-floor surface may be located at the bottom of the footings; however, where there is evidence that the groundwater table can rise to within 6 inches (152 mm) of the finished floor at the building perimeter or where there is evidence that the surface water does not readily drain from the building site, the grade in the under-floor space shall be as high as the outside finished grade, unless an approved drainage system is provided.

As for best practices, especially when a respiratory issue is involved - it is basically what everyone else mentioned - run up the foundation wall a minimum of 6", joints lapped lapped, and every hole, seam, etc... should be taped & sealed per manufacturers directions

RSS

Videos

  • Add Videos
  • View All

Twitter

Latest Activity

Alfie Davis posted a blog post
4 hours ago
Steve Last commented on Tom White's blog post Moving Forward with Home Performance
"Hopefully politicians seeking quick wins for the US economy will see home insulation improvements…"
15 hours ago
Steve Last posted a photo
16 hours ago
Judy Rachel replied to Dean Kirkland 's discussion Im looking for a blower door / duct blaster / manometer rental in So Cal
"You can borrow the equipment from the Tool Lending Library maintained by SoCalEdison.  This is…"
yesterday
Profile IconSteve Last, Paul J Anzalone Jr, Jon Traudt and 1 more joined Home Energy Pros
yesterday
Jamie Medlin replied to angela stanzione's discussion Used Weatherization and auditing equipment for sale in the group Energy Auditing Equipment for Sale, Trade or to Purchase
"Please let me know if the flowhood  still for sale. jmedlin@archonenergysolutions.com"
Friday
Jamie Medlin joined allen p tanner's group
Thumbnail

Energy Auditing Equipment for Sale, Trade or to Purchase

Discuss the pros and cons of the equipment you are interested in prior to purchase. Post equipment…See More
Friday
Laurie DiDonato posted an event
Thumbnail

HERS Rater Training Discount: Register by 1/6/17 and Get $100 Off! at Energize CT Center, North Haven, CT

January 23, 2017 to February 3, 2017
Become a HERS Rater with the NEHERS Alliance!Online Component: January 23rd-February 3rd, 2017 -…See More
Friday

© 2016   Created by Lawrence Berkeley National Laboratory.   Powered by

Badges  |  Report an Issue  |  Terms of Service