Greetings everyone! 

   I was hoping I could get some feedback with a building I am working on. The existing concrete was a 3 inch "homeowner special", so the plan is to set 2 inches of rigid foam, tubing for radiant heat, and four inches of new pour concrete.

1.) Do I need anything between the insulation and the existing concrete?

2.) The radiant pipes have ties to attach to the iron rods for the concrete, so I can only imagine that the metal goes first, then the radiant...

3.) How do I protect the rigid foam from damage from walking on it to do the other steps?

4.) Does the rigid foam boards needs to be taped between each other and to the end of the block?

This is a very exciting project and your feedback is greatly appreciated, 

    Luis

Tags: board, concrete, floor, foam, heat, installation, insulation, radiant

Views: 231

Reply to This

Replies to This Discussion

What is the issues with the "homeowner special" concrete - wavy, falling apart, or... That can easily change some answers depending on the severity 

#1 - generally not needed, though sometimes you might need a floor leveler, maybe even a crack/moisture isolation membrane

#2 - Personally I like having the radiant around the halfway mark in the slab with the metal though many simply attach it directly to the foam like is shown here http://blog.sls-construction.com/2012/common-sense-building-radiant...

#3 - use the proper foam & it can handle it - should be a high density closed cell foam

#4 - that is a very good idea

One last tip - make sure you have the pex lines pressurized while you are doing this and check them as you go - last thing you want to do is find out you have a leak after the concrete is set, while messy it is easier to fix now then later

Not sure if this would have any bearing on your project at all. Thought I would mention it though.
When we apply our coating on new concrete walls or new stucco, we always have to test the Ph level first. It must be no higher than 4, we prefer 3 or below. With concrete or stuccvo that is 5-yearsold or older, rarely an issue. Less than 5, many times an issue. It causes major bonding problems.
Again, not sure if a high Ph level concrete would cause issues with your foam or not. Possibly???
Some paint companies make a primer for high Ph surfaces. Might be a good thing to look into. Will a high Ph level concrete eat the foam??? I dont know, thats why I'm bringing it up.

RSS

Videos

  • Add Videos
  • View All

Twitter

Latest Activity

Amber Vignieri posted a blog post
8 hours ago
Evan Mills posted a blog post

Looking Back and Looking Forward: Home Energy Pros at 5 and 5000

Over the past five years, the Home Energy Pros social network has grown from a twinkle in our eyes…See More
9 hours ago
tedkidd replied to Diane Chojnowski's discussion Poll: How confident do you feel about the future of home performance?
"Thank you for sharing this trend! Full disclosure, I did NOT ask Bob to post that! If you have 2…"
9 hours ago
Bob Blanchette replied to Diane Chojnowski's discussion Poll: How confident do you feel about the future of home performance?
"I see fixed monthly grid charges continuing to increase while cost per therm/kwh/gallon remain…"
9 hours ago
Quinn Korzeniecki posted a discussion

Vent Cap Systems and SENSIT Technologies Products Added to BPI Product List

The Building Performance Institute, Inc. (BPI) has recognized four new products in its …See More
12 hours ago
Simon joined Diane Chojnowski's group
Thumbnail

Online Training

Online training coursesIf you provide ongoing online training for home performance or…See More
yesterday
Simon added a discussion to the group Energy Auditing Equipment for Sale, Trade or to Purchase
Thumbnail

Wanted - Blower and door frame kit for Minneapolis system

Hi everyone,I'm new to this line of work and have bought some equipment (Minneapolis blower door…See More
yesterday
Simon replied to Steve Mann's discussion TEC Blower Door Frame in the group Energy Auditing Equipment for Sale, Trade or to Purchase
"Hi, I'm interested, but could you send to UK?,I'd pay shipping of course. My email is :-…"
yesterday

© 2016   Created by Lawrence Berkeley National Laboratory.   Powered by

Badges  |  Report an Issue  |  Terms of Service